10-16 - Sunday - Install Insulation and Vapor Barrier - 5 workers needed from 8:00am - 6:00pm (estimated)
10-17 - Monday - Install Pipe Chairs - 5 workers needed from 8:00am - 6:00pm (estimated)
10-18 &19 - Tuesday & Wednesday - Install Rebar - 6 workers needed from 8:00am - 6:00pm (estimated)
10-20, 21,22,23 - Thursday to Sunday - Pull Rink Tubing - 5 workers needed 8:00am - 6:00pm (estimated)
10-24 - Monday - Pressure Test - No workers needed
10-25 & 26 - Tuesday & Wednesday - Install Mesh - 6 workers needed 8:00am - 6:00pm (estimated)
10-27 - Thursday - Concrete Pour - No workers needed